EMS application scenario - On/Off-grid PV+BESS+DG(Seamless)

EMS Strategy

Microgrid Power Dispatch

Microgrid Voltage and Frequency Regulation

PV Power Absorption

On/Off-grid Switching

Seamless On/off-grid switching, switching time≤20ms; DG BESS switching time 0ms. Ensure uninterrupted power supply to the critical load

On-grid to off-grid control: Upon detection of a grid failure, the Static Transfer Switch (STS) opens. The BESS switches to off-grid mode and begins discharging to support the critical load.

BESS to DG control: During BESS discharge, when the SOC drops below 10%, the DG is started and operates at 0 kW(no-load). Once the SOC falls below 5%, the BESS shuts down, and the DG automatically picks up the load, achieving 0ms switching.

Off-grid to On-grid control:  When the grid is restored and stabilized, the BESS switches back to on-grid mode. The STS closes, the DG shuts down, and the load is transferred to the grid. The BESS then begins charging from the grid and enters a standby state once fully charged.


Make energy smarter and life better!
© 2025 Shanghai UWinEra Technology Co., Ltd. All Rights Reserved
Contact Info
1-2F, Building 4, 1628 Lizheng Road, Lingang New Area, China (Shanghai) Pilot Free Trade Zone
+86-195 3352 8551
Company
Powered by Feedback Subscribe Data